If you would like to be placed on a mailing list to receive copies of public notices, please contact the Regulatory Branch, U. S. Army Corps of Engineers, P. O. Box 867, Little Rock, Arkansas 72203-0867, call (501)324-5295, or send an email to ceswl-pr-r@usace.army.mil and include your name, email address, mailing address, telephone number and indicate which counties in Arkansas or Missouri you would like to receive public notices.

NOTE: Due to budget cuts and escalating costs in processing and mailing of these public notices, we are requiring email addresses and internet access.  Only under special circumstances will we send copies of the public notices via the U. S. Postal Service.

The Public Notices are available in two electronic formats. To read the Public Notice text only (html format), click on the Public Notice number.  To view a Public Notice with its drawings, click on the Public Notice link in the attachments box. (*pdf format).

SWL 2020-00137 (GP 45)

Published May 27, 2020
Expiration date: 6/26/2020

STATE OF MISSOURI
PROPOSED ISSUANCE OF A REGIONAL GENERAL PERMIT
MAINTENANCE OF MAN-MADE LAKES AND PONDS


In accordance with Title 33 CFR 325.2 and 325.7(e), as published in the November 13, 1986, Federal Register, the U.S. Army Corps of Engineers, Little Rock District proposes to issue a regional general permit (RGP) which would authorize the maintenance of man-made lakes and ponds.  Permitted activities involve sediment removal, wave attenuation structures, shoreline stabilization, and fish and wildlife habitat improvement.  The RGP would be issued for a period of 5 years.

JOINT PUBLIC NOTICE:  This public notice is issued jointly with the Missouri Department of Natural Resources, Water Protection Program.  The Department of Natural Resources will use the comments to this notice in deciding whether to grant Section 401 water quality certification.  Commenters are requested to furnish a copy of their comments to the Missouri Department of Natural Resources, P.O. Box 176, Jefferson City, Missouri 65102.

APPLICANT:  General public, government agencies.

PROJECT LOCATION:  All Counties in Missouri – Man-made lakes and ponds in the State of Missouri, lakeward of the ordinary high water mark (OHWM).  The Lake of the Ozarks and locations in or occurring within two miles upstream of a designated outstanding state or national resource water pursuant to Missouri 10 CSR 20-7.031 are excluded from use of this RGP.  Discharges in other Waters of the U.S. are not authorized by this RGP.

AUTHORITY:  Section 10 of the Rivers and Harbors Act of 1899 (33 USC 403) and Section 404 of the Clean Water Act (33 USC 1344)

ACTIVITY (As shown on the attached permit):  This RGP authorizes the discharge of dredged or fill material associated with activities designed to improve water quality, improve fish and wildlife habitat, maintain recreational value, and extend the lifespan of man-made lakes and ponds.  This permit authorizes the removal and discharge of lakebed/pond sediment in conjunction with mechanical dredging, hydraulic dredging (including return water from such activities) and excavation activities.  The use of standard construction equipment to remove accumulated sediment is authorized by this permit.  The dredged/excavated material may be used in the construction of jetties/breakwaters, shoreline stabilization structures, fish and wildlife habitat improvement structures and other similar activities.  Fill material from off-site locations shall only be used as long as the fill material is determined to be suitable material by the Corps.  The original depths, elevations, contours and size of the water body shall not be exceeded as a result of the sediment removal process.  Dredged or excavated material must be disposed of in an upland area, a previously authorized disposal area or as described in the “Authorized Uses of Dredged/Excavated Material” section of this permit.  All material must be stabilized where it cannot be introduced into the water body or any adjacent wetland as a result of runoff, flooding, wind, or other natural forces.  This RGP will also authorize the construction of jetties, breakwaters, hard points, bank stabilization, temporary sediment basins or similar features designed to attenuate wave action not associated with sediment removal.  This permit will only be used to authorize regulated activities in existing man-made lakes and ponds located in jurisdictional Waters of the United States.  This permit does not apply to lacustrine systems that have wholly converted to a palustrine system due to lack of maintenance and/or abandonment.  This permit shall be used to authorize a project that results in an overall net benefit and does not result in a more than minimal impact to the aquatic environment.

RGPs may cause only minimal individual and cumulative environmental impacts.  Accordingly, the Little Rock District is specifically requesting public comments on reasonable limits for authorized activities to remain within minimal impact thresholds.

WETLANDS/AQUATIC HABITAT:  Generally, compensatory mitigation will not be required for impacts to wetlands formed as a result of erosion or sedimentation within the impoundments.   Reference Regulatory Guidance Letter (RGL) 18-01, Determination of Compensatory Mitigation Credits for the Removal of Obsolete Dams and Other Structures from Rivers and Streams concerning loss of wetlands due to ecosystem restoration.

ADDITIONAL INFORMATION:  Additional information about this application may be obtained by contacting James Reenan, Missouri State Regulatory Office, 101 East High Street, Suite 202, Jefferson City, Missouri 65101, at (816) 389-3832 or via email at james.s.reenan@usace.army.mil.  All comments to this public notice should be directed to the above address.

CRITERIA FOR AUTHORIZATION:  All activities authorized by this RGP require written pre-construction notification (PCN) to the Corps.  In order for the PCN to be determined complete it must include applicant contact information, location map, project drawings, proposed mitigation (if required), and a description of any known or suspected, unsafe contaminants occurring within the dredged material that is part of the overall project.  Applications for Section 404 authorization under this RGP will be evaluated on a case-by-case basis.  The Corps reserves the right to require an individual permit application in circumstances where the activity is determined to have more than a minimal adverse impact on the aquatic environment or when the proposed project does not meet the cited criteria.

COMPLIANCE WITH OTHER LAWS:  All applicable statutes, regulations, and administrative policies and agreements, including the National Environmental Policy Act of 1969 as amended, will be considered in the decision to issue the regional general permit.

CULTURAL RESOURCES:  No activity which may affect historic properties listed, or eligible for listing, in the National Register of Historic Places is authorized, until the District Engineer has complied with the provisions of 33 CFR Part 325, Appendix C and applicable guidance.

ENDANGERED SPECIES:  Projects eligible for authorization under this RGP may be located within the known range of Federally listed, threatened or endangered species.  All Projects located within the known range of any Federally listed species will require consultation with the U.S. Fish and Wildlife Service, pursuant to Section 7 of the Endangered Species Act, to determine the potential effects on a particular species or critical habitat, unless Section 7 consultation addressing the effects of the proposed activity has been completed.

PUBLIC INTEREST REVIEW:  The decision to issue this RGP will be based on an evaluation of the probable impact including the cumulative impacts of the proposed activity on the public interest.  That decision will reflect the national concern for both protection and utilization of important resources.  The benefits which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments.  All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, cultural values, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs and, in general, the needs and welfare of the people.  The evaluation of the impact of the activity on the public interest will include application of the guidelines promulgated by the Administrator, Environmental Protection Agency under authority of Section 404(b) of the Clean Water Act (33 USC 1344).  The Corps of Engineers is soliciting comments from the public; Federal, state, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity.  Any comments received will be considered by the Corps of Engineers to determine whether to issue, modify, condition or withdraw this RGP proposal.  To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above.  Comments are used in preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act.  Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

COMMENTS:  This notice is provided to outline details of the above described activity so that the Little Rock District may consider all pertinent comments prior to determining if issuance of a permit would be in the public interest.  Any interested party is invited to submit to the Missouri State Regulatory Office written facts or objections relative to the activity on or before the public notice expiration date.  Comments both favorable and unfavorable will be accepted and made a part of the record and will receive full consideration in determining whether it would be in the public interest to issue the RGP.  Copies of all comments, including names and addresses of commenters, may be provided to the applicant. Comments should be emailed to james.s.reenan@usace.army.mil.

RGPs may cause only minimal individual and cumulative environmental impacts.  Accordingly, the Little Rock District is specifically requesting public comments on reasonable limits for authorized activities to remain within minimal impact thresholds.

PUBLIC HEARING:  Any person may request, in writing, prior to the expiration date of this public notice, that a public hearing be held to consider this RGP.  Such requests shall state, with particularity, the reasons for holding a public hearing.

Enclosure