Mariners are advised that intermittent delays may be
experienced at Toad Suck Lock and Dam (No. 8) NM 155.9, April 2 through April
4, from 7:00 a.m. to 6:00 p.m. These
delays are due to dive inspections. The
inspections are expected to be completed as scheduled, however, unforeseen
issues could require additional time.
Questions or requests for additional information
concerning this notice should be directed to James McKinnie in the Little Rock
District Office, at (501) 324-5739 or (501) 324-5096, or you may email
CESWL-OP-OM@usace.army.mil.
//signed//
Kevin J. McDaniels
Chief, Operations Division
Release no. SWL 16-29