Mariners are advised that continued intermittent delays may be experienced at Murray Lock and Dam (No. 7) NM 125.4 daily 7:00 a.m. to 5:30 p.m. through June 17, while repair of the parapet wall takes place.
The lock will be closed to navigation traffic from 8:00 a.m. to 11:00 a.m. on June 18 to place concrete on the upstream long wall. If work is completed ahead of schedule, normal operations will resume at that time. However, unforeseen problems could require additional time; therefore intermittent delays may be experienced until 5:00pm.
Questions or requests for additional information concerning this notice should be directed to James McKinnie in the Little Rock District Office, at (501) 324-5739 or (501)324-5096, or you may email CESWL-OP-OM@usace.army.mil.
//signed//
John A. Balgavy, P.E.
Chief, Operations Division
Release no. SWL 13-25