During inspection prior to performing a maintenance dewater, the Little Rock District discovered that the existing center post supporting 50′ Stop Logs had catastrophically failed. After verifying similar failures at other locations along the McClellan-Kerr Arkansas River Navigation System (MKARNS), SWL determined that the stop log slots at all affected locks would be converted to support 110′ Stop Logs.
The District utilized design resources including enterprise resources from LRL, LRP, INDC, and AE design firms to complete designs, and solicited and awarded a Construction MATOC with $200M of capacity to a pool of technically qualified construction firms. The navigation closure window for construction phases is 15 June – 30 September annually.
To date, six locks have been awarded for construction, four are in design, one is completed, and the final location will begin design in Q4 FY26.
Budget Information
Authorized Total Project Cost $186,000,000
Funds Utilized to Date $130,200,000
Remaining Funds $55,800,000
Federal Cost $186,000,000
Current Status
- Dardanelle, Trimble, Ozark, Murray, Toad Suck, and Ormond Locks are scheduled to complete construction CY26.
- Lock 2, Hardin, Sanders, and Maynard Locks are scheduled to complete design in CY26.
- Montgomery Point scheduled to begin design Q4 FY26.
★ Future Value to the Nation Without project completion, locks will be unable to be dewatered for inspection or emergency closures. Underwater components cannot be properly inspected and maintained, placing entire structures at risk. In the event of catastrophic failure (e.g., miter gate failure), replacement would be impossible and could close the river indefinitely.