Little Rock District Top 5 Priority Projects

Advancing critical infrastructure, energy, and navigation across the district.

Total Projects

5 Active

Total Investment

$774M+

Power Capacity

+132 MW

Locks Upgraded

12 Locks

Project 1 of 5

MKARNS 110′ Stop Log Slot Conversions

McClellan-Kerr Arkansas River Navigation System — $186M infrastructure modernization across 12 locks

Authorization Annual Civil Works Appropriations
Project Sponsor Full Federal Project
Location MKARNS, Arkansas & Oklahoma

During inspection prior to performing a maintenance dewater, the Little Rock District discovered that the existing center post supporting 50′ Stop Logs had catastrophically failed. After verifying similar failures at other locations along the McClellan-Kerr Arkansas River Navigation System (MKARNS), SWL determined that the stop log slots at all affected locks would be converted to support 110′ Stop Logs.

The District utilized design resources including enterprise resources from LRL, LRP, INDC, and AE design firms to complete designs, and solicited and awarded a Construction MATOC with $200M of capacity to a pool of technically qualified construction firms. The navigation closure window for construction phases is 15 June – 30 September annually.

To date, six locks have been awarded for construction, four are in design, one is completed, and the final location will begin design in Q4 FY26.

Budget Information

Authorized Total Project Cost $186,000,000
Funds Utilized to Date $130,200,000
Remaining Funds $55,800,000
Federal Cost $186,000,000

Current Status

  • Dardanelle, Trimble, Ozark, Murray, Toad Suck, and Ormond Locks are scheduled to complete construction CY26.
  • Lock 2, Hardin, Sanders, and Maynard Locks are scheduled to complete design in CY26.
  • Montgomery Point scheduled to begin design Q4 FY26.
★ Future Value to the Nation Without project completion, locks will be unable to be dewatered for inspection or emergency closures. Underwater components cannot be properly inspected and maintained, placing entire structures at risk. In the event of catastrophic failure (e.g., miter gate failure), replacement would be impossible and could close the river indefinitely.
Project 2 of 5

MKARNS Three Rivers Project

Arkansas & Desha Counties, AR — $334M containment and channel restoration project protecting the MKARNS entrance channel

Authorization America's Water Infrastructure Act of 2018, Section 1401
Project Sponsor Full Federal Project
Location Arkansas & Desha Counties, Arkansas

The Three Rivers project is located on the MKARNS between the White and Arkansas Rivers, just upstream of the Montgomery Point Lock & Dam in southeast Arkansas. Modifications to the Mississippi River have steepened the stream slope and accelerated water velocity, causing the Mississippi to migrate into the White River, which then overflows into the Arkansas River.

The project includes four construction components: restoration of a historic relief channel between the White and Arkansas Rivers with a hydraulic weir (crest elevation 145 ft.); a 2.4-mile containment structure built to an elevation of 157 ft.; modification of the Owens Lake containment structure; and improvement of the LaGrue Culverts. Approximately 20 acres of agricultural land will be converted to bottomland hardwood forest to meet mitigation requirements.

Budget Information

Authorized Total Project Cost $333,761,000
Non-Federal Sponsor Cost N/A
Non-Federal Funding Received to Date $346,849,162
Federal Cost $346,849,162

Current Status

  • Phase 1 (hydraulic weir, crest elevation 145 ft.) completed October 2025.
  • Phase 2 (2.4-mile containment structure, Owens Lake modification, and LaGrue Culverts) awarded December 2024; scheduled completion January 2028; currently on track to finish September 2026.
★ Future Value to the Nation This project will dramatically reduce the risk of a cutoff forming near the entrance channel of the MKARNS between the Arkansas and White Rivers, protecting the long-term viability of the navigation system and the regional economy it supports.
Project 3 of 5

Bull Shoals Major Equipment Replacement

Bull Shoals Lake Dam Powerhouse — $114M rehabilitation increasing capacity from 340 MW to 362 MW

Authorization WRDA 2000, Section 212 — Hydroelectric Power Project Funding
Project Sponsor SPRA / Southwestern Power Administration (SWPA)
Location Bull Shoals Lake Dam Powerhouse, Arkansas

Bull Shoals Dam Powerplant is an 8-unit hydroelectric plant with a combined installed power capacity of 340 MW. This project will increase power capacity to 362 MW. The plant began commercial power generation in 1952, with final installation of all generating units completed in 1963.

The Major Equipment Replacement project is scoped to replace and rehabilitate major components including turbines, generators, transformers, and other ancillary equipment that have reached the end of their service life. Design funds were approved in May 2018, with additional approvals in July 2022 and January 2025.

The Turbine Replacement and Generator Rewinds will uprate Units 1–4 from 48.4 MVA to 54 MVA, and current turbine runners will be replaced with aerating runners to improve dissolved oxygen downstream of the dam.

Budget Information

Authorized Total Project Cost $113,917,500
Non-Federal Sponsor Cost $113,917,500
Non-Federal Funding Received to Date $13,917,500
Federal Cost $0

Current Status

  • Powerhouse bridge crane replacement contract awarded November 2023 to Garco-Wemco JV; new crane in final fabrication; on-site work begins June 2026.
  • SWPA collecting funds for the Units 1–4 Turbine Generator project; $100M approved. Remaining $93M will be requested in the current funding cycle; SWL does not expect funding until FY28–FY29 at the earliest.
  • Transformer design ongoing; 60% design completed January 2026. Existing oil-filled GSU transformers will be replaced with three-phase SF6 gas-insulated transformers (GITs).
★ Future Value to the Nation This project will increase power generating capacity at Bull Shoals Dam Powerhouse, improve dissolved oxygen downstream of the dam, and reset the service life of key components to improve unit reliability for power customers.
Project 4 of 5

Norfork Major Rehabilitation

Norfork Lake Dam Powerhouse — $114M rehabilitation increasing capacity from 80 MW to 93 MW

Authorization WRDA 2000, Section 212 — Hydroelectric Power Project Funding
Project Sponsor SPRA / Southwestern Power Administration (SWPA)
Location Norfork Lake Dam Powerhouse, Arkansas

Norfork Dam Powerplant is a 2-unit hydroelectric plant with a combined installed power capacity of 80 MW. This project will increase power capacity to 93 MW. The plant began commercial power generation in 1944 and is one of USACE’s oldest hydroelectric facilities.

The Major Rehabilitation project replaces and rehabilitates major components including turbines, generators, transformers, and ancillary equipment. Design funds were approved in July 2016; the first construction funding package was approved November 2018, with additional approvals in January 2022 and July 2024.

The Turbine Replacement and Generator Rewind contract ($52.6M currently), awarded September 2022, will uprate both units from 40 MW to 46.5 MW and replace existing turbine runners with aerating runners to improve dissolved oxygen downstream of the dam.

Budget Information

Authorized Total Project Cost $113,500,000
Non-Federal Sponsor Cost $113,500,000
Non-Federal Funding Received to Date $102,000,000
Federal Cost $0

Current Status

  • Turbine Generator contractor (Voith Hydro) mobilized January 2026 to begin site work.
  • Unit 2 outage began February 12, 2026; scheduled duration of 14 months.
  • Additional contract work ongoing with McKenzie Construction to upsize the cable tunnel cooling system to match increased cooling load within the tunnel.
★ Future Value to the Nation This project will increase power generating capacity at Norfork Dam Powerhouse, improve dissolved oxygen downstream of the dam, and reset the service life of key components to improve unit reliability for power customers.
Project 5 of 5

Beaver Dam Generator Rewind

Beaver Lake Dam Powerhouse — $27M restoration returning full 112 MW generating capacity after stator fault

Authorization WRDA 2000, Section 212 — Hydroelectric Power Project Funding
Project Sponsor SPRA / Southwestern Power Administration (SWPA)
Location Beaver Lake Dam Powerhouse, Arkansas

Beaver Dam Powerplant is a 2-unit hydroelectric plant with a combined power capacity of 112 MW. This project restores full generating power capacity after Unit 2 experienced a stator fault in August 2016. The plant began commercial power generation in May 1965.

The generator rewind contract was awarded to Andritz Hydro on September 30, 2021, for $11.6M. The project encountered numerous unforeseen challenges including HAZMAT abatement, Unit 2 rotational issues, and the need to stiffen both units’ stator frames. The resulting contract amount is currently $18.3M, with an additional modification ($1.4M) negotiated and awaiting award.

Additional funding to complete the project was approved by SWPA and SPRA in October 2025. SWL is awaiting final execution of sub-agreement modification 431-M002-S321-M002 for an additional $2,500,000.

Budget Information

Authorized Total Project Cost $27,300,000
Non-Federal Sponsor Cost $27,300,000
Non-Federal Funding Received to Date $24,800,000
Federal Cost $0

Current Status

  • Unit 2 returned to service April 2025 after being out of service for 8+ years due to stator fault.
  • Unit 1 outage began May 2025; reassembly of unit now complete following generator rewind work.
  • Commissioning of Unit 1 ongoing; return to service expected mid-March 2026.

Upcoming Actions

  • Completion of wet commissioning of Unit 1 and special field testing.
  • Finalize execution of sub-agreement modification 431-M002-S321-M002 ($2,500,000).
★ Future Value to the Nation This project restored full generating power capacity (112 MW) to Beaver Dam Powerhouse, prepared the generator for future power uprates if deemed feasible, and reset the service life of key components to improve unit reliability for power customers.