Project Information Report Completed
The Project Information Report was completed. The Benefit to Cost Ratio was 0.43 which is below the requirement for assistance. The project is ineligible for rehabilitation assistance. Rehabilitation Assistance projects must have a favorable Benefit-to-Cost Ratio (i.e., > 1.0) in accordance with the Principles and Guidelines contained in Chapter 6, ER 1105-2-100, regarding National Economic Development (NED) Benefit Cost Analysis.