McLean Bottoms Levee

McLean Bottom Levee District - Little Rock District USACE

McLean Bottom Levee District No. 3

Arkansas River | Mixed Operation: USACE & Local District

Stream

Arkansas River

Bank Position

Right Bank

Operators

USACE & Local District

Current Status

Substantially Complete

Background Information

The McLean Bottom Levee System was damaged during the May/June 2019 Arkansas River Flood Event, leading to the Levee Sponsor submitting a Public Law (PL) 84-99 Rehabilitation Assistance request to the U.S. Army Corps of Engineers (USACE) Little Rock District (SWL).

System Segments

This McLean Bottom Levee system is divided into three segments:

  • McLean Bottom Levee District No. 3 - Locally operated and maintained by the McLean Bottom Levee District No. 3
  • Six Mile Diversion Levee - USACE operated and maintained
  • McLean Bottom Levee and Pumping Station - USACE operated and maintained
National Levee Database: Detailed technical information about this levee system is available in the National Levee Database.

View in National Levee Database

Current Action

Status: Engineering and Design funding has been received to begin work on the McLean Bottom levee repair project.

Project Purpose

The purpose of this rehabilitation project is to repair the levee system to its authorized level of flood risk management.

Levee System Location Map

McLean Bottom Levee System Location Map

Project Timeline

16 July 2021
Project Substantially Complete

Project is substantially complete, pending establishment of turf.

11 January 2021
Breach Repairs Complete

Upstream and downstream breaches substantially repaired and awaiting vegetation establishment.

28 May 2020
Cultural Resource Concurrence

Cultural Resource Concurrence received.

16 May 2020
Contract Award for Final Repair

Construction contract awarded for final repair work.

10 April 2020
Initial Repairs Completed

Initial repairs providing 25-year level of protection completed.

16 March 2020
Design and Repair Work Continues

Initial repairs and E&D work for final repair continue.

11 March 2020
Final Level Repairs Design Complete

Final level repairs design plan complete.

24 February 2020
Memphis District Begins Downstream Repair

USACE Memphis District begins initial repair (25-year level of protection) on downstream breach.

17 February 2020
Setback Levee Design Completed

Design for setback levees completed.

14 February 2020
Vicksburg District Begins Upstream Repair

USACE Vicksburg District begins initial repair (25-year level of protection) on upstream breach.

28 January 2020
Rights of Entry Obtained

Rights of Entry for construction obtained by levee district.

09 January 2020
E&D Work Continues

Engineering and Design work continues.

20 December 2019
Topographical Surveys Completed

Topographical surveys completed for breach area. These surveys will allow the E&D team to better define quantities needed for construction.

11 December 2019
Initial Repair Approved

Initial repair approved and funding received. The initial repair consists of two setback levees constructed around the landside of the two breaches in the levee.

05 December 2019
Rights of Entry Obtained

Rights of Entry (ROE) obtained. E&D work continues.

December 2019
Cooperation Agreement Signed

The Cooperation Agreement between the local sponsor and the Little Rock District Corps of Engineers was signed. Rights of Entry are being obtained.

22 November 2019
E&D Progress Update

Engineering and Design (E&D) work continues for rehabilitating the McLean Bottom levee system. The team is still anticipating to be done with the E&D process by early 2020.

21 November 2019
Stakeholder Engagement Meeting

Levee Stakeholder Engagement Meeting held in Paris, AR. Meeting included local sponsor and affected farmers impacted by the flooding. The attendees were informed of the P.L. 84-99 process and updated on the status of the project.

13 November 2019
District Cooperation Agreement Signed

Cooperation agreement between USACE and McLean Bottoms Levee District No.3 signed.

07 November 2019
Project Kickoff Meeting

Project kickoff meeting with local sponsor – McLean Bottom Levee District No. 3. Meeting conducted to review the rehabilitation process, cooperation agreement, cultural resource and real estate requirements.

21 October 2019
Project Delivery Team Kickoff

Project Delivery Team (PDT) kickoff meeting conducted with design team members. E&D work is ongoing for rehabilitating the McLean Bottom County Levee District No. 3 system. The team is anticipating to be done with the E&D process by early 2020. Once E&D is completed, a construction contract will be advertised and awarded to repair the system.

16 October 2019
E&D Funding Received

Engineering and Design funding received.

09 October 2019
Project Information Report Approved

The Project Information Report has been approved by the USACE Southwestern Division Commander, BG Owen. Engineering and Design (E&D) funding has been requested. Once funding has been received, the USACE team will coordinate with the Levee Sponsor on the design of the overall levee repair project.

17 June 2019
Initial Assessment Completed

An initial site damage assessment and economic analysis has been completed by the USACE Little Rock District (SWL) team. From this initial assessment, the team has determined that there are damages to the levee system that are eligible for Public Law (PL) 84-99 Rehabilitation Assistance.

Additional Resources