18 June 2021 - Project complete.
11 January 2021 - Breach substantially repaired and awaiting vegetation establishment
21 August 2020 - Levee crest and roadway repair continue
15 June 2020 - Breach and slide repair complete
30 April 2020 - Final repair design plans complete (BCOES Certification)
31 March 2020 - Contract award for final repair
16 March 2020 - Repairs to breach at 5th Street and adjacent slide continue, design for other damaged areas continue.
27 February 2020 - Final repairs to breach at 5th Street and adjacent slide begin.
10 February 2020 - Design for final repairs of breach and levee complete. Contract with Tennessee Valley Authority (TVA) for final repairs to breach at 5th Street and adjacent slide to originally designed level of protection. Design work continues on additional damage.
07 January 2020 – Temporary setback levee construction completed. The setback levee will provide a minimal level of protection until the final repair is completed.
20 December 2019 – USACE inspection of levee completed.
09 December 2019 - Contractor onsite, construction of 25 year protection begins to place a temporary setback levee around the breached area.
5 December 2019 - Contract with Tennessee Valley Authority (TVA) for initial repairs to breach at 5th Street. Initial repair provides a 25 year protection level of protection.
28 October 2019 – First Quarter Flood Supplemental funds received.
17 June 2019 – An initial site damage assessment was completed by the USACE Little Rock District (SWL) team. From this initial assessment, the team has determined that there were damages to the levee system that are eligible for repair.