Teamwork made Montgomery Point a reality
Along
with the promise of an increased workload for Little Rock District,
Montgomery Point Lock and Dam has brought with it challenges that
could only be accomplished through teamwork. And the challenges started
early in the life of the project.
In 1980
the district was asked to look into a low-water problem in the White
River Entrance Channel. In September 1986, the district began a feasibility
study on the possibility of building a dam to correct the problem.
"It
took a lot of people and time to get that study done on time, but
we did it," said Chris Hicklin of Planning Division. "One
thing that got us so far ahead in the study is that we quickly identified
the environmental issues that were involved in the project.
"Then
we began getting other state and federal agencies involved in the
story. It really paid off in the end, because they were already familiar
with and supportive of the project right up front."
The Montgomery
Point Project managers have led by example. Hicklin was the original
project manger for Montgomery Point, but then he passed the reins
to Randy Hathaway, who managed the project for more than six years.
Eighty-seven
people in the district office and 40 people from Harza, an A-E firm
designing the dam and navigation gates, have been involved in Montgomery
Point.
"That
gives you an idea of the size of the project. The job is just too
big for one person or even one team," Hathaway said.
"We
actually have teams working within teams. Even though there are turf
battles every once in a while, I have seen everyone put those aside
to do what is best for the project and the district."
The teamwork
that was instrumental in the beginning of Montgomery Point has carried
over into every aspect of the project.
"It
has been close to 30 years since this district designed a lock and
dam," said Elmo Webb, a civil engineer in the Geotechnical Branch
who worked on the project. "Most of the people with design expertise
and experience from constructing the locks and dams on the navigation
system had retired."
"The
most challenging thing was to extend our thought processes. Almost
every design phase of this project had been performed before by this
district, but not at the magnitude that we were going to have to do
it."
The learning
curve was short for the designers involved in the project.
"It
was very stressful being a part of this project team and trying to
take lessons learned from other designs and designers without making
mistakes of your own," said Exa Hartman, an electrical engineer
in Design Branch.
"I
believe we needed the time to design and redesign so that we could
make mistakes in the beginning, correct them and end up with the best
possible product in the end."
The coordination
did not stop at the district boundaries, architectural and engineering
contractors, other Corps districts and laboratories as well as a massive
effort by district employees was needed to get the design done.
"It
has been difficult because this is a large, first-of-its-kind project,
and we are still basically a small district with a small design staff,"
said Tom Clement, technical manager for the project.
"It
takes so many people to do a project of this size. We were always
needing subject matter experts, so we were always pulling in the best
people we had. Keeping up with it all was a big job."
Many
of the people who have helped with Montgomery Point did it in addition
to working on other projects.
"My
major challenge has been supporting all the designers and technicians
during the entire design phase of the project in addition to supporting
the numerous other CADD-based project that have passed through Design
Branch during the design of Montgomery Point," said Royce West,
CADD system manager in the Architect and Support Section.
"It
was difficult to stay focused on the design throughout the project
to reach the final plans and specifications stage," said Mark
Emmerling, lead electrical engineer for the team. "Being a part
of the project required a strong will to follow through and complete
all the required tasks."
In addition
to the challenges experienced by Montgomery Point team members, they
also recognize the benefits that come from working on the project.
"This
project was one of my first assignments at Little Rock District, and
it has enabled me to work with a very skilled team of engineers and
technicians," said Larry Winters, a structural engineer in Design
Branch. "It has been great on-the-job training to see and participate
in the innovative team effort that has been required to solve complex
design problems."
The uniqueness
of the project also makes all the hard work worthwhile.
"I
know that working on the project makes me part of what is probably
the last major design effort that the Little Rock District will do,"
said Greg Yada of Hydrology and Hydraulics Branch.
As the
plans and specifications are completed, the focus changes from design
to contracting.
"Now
my major challenge is to keep the solicitation and award process running
as smoothly as possible and on time," said Virginia Moore of
the A-E Construction Contracts Branch.
Because
of the teamwork, everyone who has worked on the Montgomery Point project,
from study leaders to CADD operators, has a vested interest in seeing
construction begin, and eventually seeing the product completed.
"A
lot of experience and confidence has been gained through this design
process, and a lot more will be gained in the construction of this
project," Webb said. "Five to six years from now, when this
project is operational, there will be a lot of proud people in the
district."