Study Background
The
city of Springfield,
Missouri, and the Little
Rock District, US Army Corps of Engineers are partnering in a feasibility
study of the Jordan
Creek watershed for the purposes of flood damage reduction
and ecosystem restoration. The $3 million, 50-50 cost-shared feasibility
study began in May 2004 with the signing of a feasibility cost sharing
agreement between the Corps and Springfield. The study will define problems
and opportunities, describe and evaluate alternative plans, and identify
a recommended plan for construction. It will take over four years to
complete the study.
If
a plan is found to be economically justified (for ecosystem restoration,
the value of outputs must equal their costs), environmentally acceptable,
based on sound engineering principles, and acceptable to the city with
Federal and local sponsor funding obtained, the project can proceed
to design. Following Congressional authorization and funding for the
project, a project cooperation agreement would be signed between the
Corps and Springfield, to allow for construction of the project.
Jordan
Creek has flooded many times. During the flood of July 2000, there were
an estimated $1.85 million in flood damages including the interruption
of traffic on main city thoroughfares and rail lines. The existing channels
and covered conduits are inadequate to carry a flow that has increased
with the growing development in the Jordan Creek watershed. Flood control
measures to be considered include structure relocations, detention ponds,
open channels, and in congested areas, enlarging underground culverts.
July 2000 Flood Photos
- Click on the thumbnails to see a larger photo.
Likewise,
development along Jordan Creek has decreased riparian habitat and water
quality. Opportunities exist to restore ecosystem habitat and improve
water quality by measures such as constructed wetlands, water quality
sediment basins, and riparian enlargement. In conjunction with ecosystem
restoration and flood damage reduction, increased recreation opportunities
such as hiking or biking trails could be considered.
Current
Status
The
Springfield, Missouri, Jordan Creek Watershed project is in the second
of a two-phase
study process. The first phase, a Reconnaissance Study, was completed
in January 2003, which concluded that a federal project could potentially
solve the problems identified in the Jordan Creek Watershed. As a result,
the Feasibility Study was initiated in May 2004 with the signing of
a Feasibility Cost Sharing Agreement. The study will be accomplished
according to the Corps of Engineers 6-step
planning process:
· Specify
Problems and Opportunities
· Inventory
and Forecast Conditions
· Formulate
Alternative Plans
·
Evaluate Effects of Alternative Plans
· Compare
Alternative Plans
· Select
Recommended Plan
The six steps provide a framework for planning and are not necessarily
sequential. We are currently working within the first three steps.
Surveys were mailed to residences within the floodplain to obtain information
regarding value of property and their potential flood damages. Similarly,
surveys are being mailed to the businesses and industry to determine
flood damages that might occur and that might be prevented with a flood
protection project. The depth, extent, and frequency of existing conditions
flooding is being determined. When plans are developed, we will compute
the reduction in damages that would occur with each plan. The plans
would then be compared based on their costs. Environmental investigations
are underway to determine whether any environmental cleanup would need
to be done prior to project construction.
A public scoping meeting is a critical part of these first steps in
the planning process. The public was invited to assist in specifying
problems and opportunities related to flood damage reduction and ecosystem
restoration. The public is requested to provide information on the existing
conditions, anticipated future activities, and inventory of the floodplain
and watershed. Public views and comments are integral to the process
of developing and comparing the plans (including the no-action plan
to which all plans are compared) to address the identified problems
and opportunities. Conceptual
plans have been developed to start the process of compiling
ideas to solve the flood damage and ecosystem restoration problems that
have been identified to-date. The public scoping meeting was held on
October 26, 2004, from 5 to 7 pm, at the Ozarks Technical Community
College, Information Commons West Room 100B (1001 E Brower).
Review Plan
The
Review Plan was approved by
Southwestern Division on April 27, 2010. The Review Plan presents the
process for agency technical review (ATR) and independent external peer
review (IEPR) for the Jordan Creek, Springfield, Missouri, feasibility
study. These review processes are essential to improving the quality of
our products.
Contact
Information
Comments,
questions, or concerns may be mailed to:
U.S. Army Corps of Engineers, Little Rock
Attention: Julia Smethurst
P.O. Box 867
Little Rock, Arkansas, 72203-0867
Email: ceswl-pm-smfs@usace.army.mil
|