Dam Major Rehabilitation Project (Phase 1)
PIEDMONT,
Mo., May 30 – The first phase of the Clearwater Dam Major Rehabilitation
Project is underway. The contract for this phase the project was awarded
to ACT (Advanced Construction Techniques), which in turn sub-contracted
part of the work to Quadri Construction Company of Ellsinore, Mo. Phase
one is expected to take about one year to complete.
The initial work consists of clearing and grubbing trees and brush in
the work area. Then a 30 foot wide work bench about 4,000 feet long will
be constructed of crushed rock on the north face of the dam. The work
bench will provide a level work area for ACT’s drill rigs to travel the
full length of the dam during the drilling and grouting that will follow.
Several drill rigs will be necessary. Once a hole is drilled, grout (a
cement mixture) will be pumped in. The grout will help stabilize the area
for the new concrete cut off wall that will be installed in the second
phase of work. The grout fills voids that may exist in the ground and
bedrock below the dam.
Construction of the work bench will start on the west end of the dam and
proceed the full length of the dam. Several dump trucks will be needed
to haul in the material, so if you are traveling in the area please use
extreme caution and watch out for trucks entering and exiting the work
area.
Phase two of the project is expected to start as soon as phase one is
completed. This phase will consist of the actual concrete cut off wall
being installed. Completion of the entire project is expected to take
about five years.
With summer upon us and many visitors in the area, please be careful while
visiting the lake. As always, your safety is our number one concern. If
you have questions concerning the major rehab project visit http://www.swl.usace.army.mil/projmgt/cwmajorrehab.html.
To make advanced camping and shelter reservations, call Reserve America
at 1-877-444-6777. Reservations can also be made on the Internet at www.ReserveUSA.com.
For more information about water levels and recreation at Clearwater,
write the Corps at RR 3 Box 3559-D, Piedmont, MO 63957, or call 573-223-7777.
General Lake information is on the Internet at www.swl.usace.army.mil/parks/clearwater.
For the forecast on Black River conditions check the Lower Mississippi
River Forecast Center at http://www.srh.noaa.gov/lmrfc/forecast/tributaries/status_black.shtml.
|