Dewatering Well Installation |
5/12/99 12:53:49 PM Drilling well #76
|
 |
Electrical Service |
5/12/99 12:53:11 PM Installing electrical service to the site.
|
 |
Cofferdam Cell Construction |
5/12/99 12:52:17 PM Cells 46, 45, 40-36 (r to l). Note 4-cell gap remaining.
|
 |
Dewatering Well Installation |
5/12/99 11:45:24 AM Drilling well #76
|
 |
Scour Monitoring Surveys |
5/12/99 7:40:19 AM JAJ/A's survey boat performing hydrographic survey near Cell 9.
|
 |
Cofferdam Cell Construction |
5/7/99 1:35:27 PM Cell 10 (foreground). Water inside cell has been displaced by cell fill material.
|
 |
Cofferdam Cell Construction |
5/7/99 1:27:45 PM Cells 39 and 40.
|
 |
Cofferdam Cell Construction |
5/7/99 1:27:28 PM Cells 45 and 46.
|
 |
Cofferdam Cell Construction |
4/29/99 12:59:08 PM Construction of connecting Arc 8A. Note how upstream sheets are overlapped to stop flow. Downstream sheets are then placed and driven before closing and driving upstream sheets.
|
 |
Cofferdam Cell Construction |
4/29/99 12:50:41 PM Cells 9-12 (r to l).
|
 |
Cofferdam Cell Construction |
4/24/99 10:05:08 AM Setting of template for Cell 13. Note how floatation material has been moved from below the lower ring to below the upper ring as a result of the accident which occurred in February 1999. The template is more stable with this configuration.
|
 |
Flow Deflector |
4/24/99 9:25:55 AM Placement of random fill behind flow deflector to elevation 116.0.
|