Montgomery Point Lock and Dam
US Army Corps of Engineers
Little Rock District

These photographs were taken of construction activities on-going at the Montgomery Point Lock and Dam work site. The project is located on the White River at N.M. 0.5 of the McClellan-Kerr Arkansas River Navigation System. The prime contractor is J.A. Jones/Atkinson-Constructors, A Joint Venture.

The work consists of construction of a new lock, dam, control tower, mooring area, diversion channel, channel revetments and dikes


Job Montgomery Point Lock & Dam
Job Number mpld
Description Construction

Photo Caption Description
Cofferdam Cell Construction 5/27/99 7:30:00 AM
Placing sheets in Cell 42.
Cofferdam Cell Construction 5/26/99 3:07:23 PM
Phase 3 cofferdam construction activities.
Sheet Pile Cutoff Wall 5/26/99 3:06:44 PM
Placing random fill between Cell 46 and embankment portion of cofferdam in preparation of construction of cutoff wall.
Temporary Electrical 5/26/99 9:31:58 AM
Trenching and placing conduit along embankment portion of cofferdam near the Project Office.
Sheet Pile Cutoff Wall 5/24/99 1:37:31 PM
Placing sheets in cutoff wall at Cell 1.
Miscellaneous 5/22/99 1:02:44 PM
View toward upstream leg of cofferdam.
Cofferdam Cell Construction 5/20/99 2:32:17 PM
Sheets 2 and 3 in Cell 12. These sheets were out of interlock and were replaced.
Sheet Pile Cutoff Wall 5/20/99 1:01:27 PM
Placing sheets in cutoff wall at Cell 1.
Cofferdam Cell Construction 5/20/99 12:14:35 PM
Connecting Arc 11A.
Cofferdam Cell Construction 5/20/99 12:13:37 PM
View toward downstream leg.
Cofferdam Cell Construction 5/20/99 12:13:16 PM
Completed cell cap material from Cell 15.
Miscellaneous 5/19/99 9:58:41 AM
"Island" left where cofferdam alignment turns away from diversion channel alignment.
Cofferdam Cell Construction 5/19/99 9:52:02 AM
Compacted roadway portion of cell cap.
Cofferdam Cell Construction 5/19/99 9:47:55 AM
Placing cell cap material.
Cofferdam Cell Construction 5/19/99 9:42:49 AM
Placing cell cap material.
Sheet Pile Cutoff Wall 5/19/99 8:04:43 AM
Placing sheets in cutoff wall at Cell 1.
Dewatering Well Installation 5/18/99 2:12:56 PM
Installing well #73.
M/V Gist Wilbur 5/14/99 1:10:02 PM

Photographs were taken by Mitch Eggburn and Joe Goodson of the
Montgomery Point Lock and Dam Resident Office