| Photo |
Caption |
Description |
 |
crest gates |
2/18/2003 2:32:26 PM installing crest gate # 9 at the Nav Pass
|
 |
Navigable Pass |
2/18/2003 1:24:42 PM Conduit and control panels in navigable pass gallery.
|
 |
Navigable Pass |
2/18/2003 1:23:12 PM Local control panel for crest gate operation in navigable pass gallery.
|
 |
Revetment 2.0R |
2/18/2003 12:50:34 Dragline cutting down spoil to elevation 130.0 and depositing it into the White River for the Dredge Boat Bill Holman to pick up.
|
 |
Navigable Pass |
2/13/2003 11:05:52 AM Area still needing to be filled with R5000.
|
 |
Scour slab |
2/13/2003 11:05:16 AM R5000 placed along scour slab downstream of the navigable pass.
|
 |
O & M Area |
2/13/2003 11:01:42 AM Placing compacted pervious fill in O & M Work Area. Placing anchoring rods in O&M work area.
|
 |
Revetment 2.0R |
2/13/2003 10:45:04 AM Dredge operating at or about STA. 55+00
|
 |
Revetment 2.0R |
2/13/2003 10:44:16 AM Crane being made ready to crawl on to barge.
|
 |
Aerial February 2003 |
2/12/2003 10:24:30 AM Cofferdam from downstream north bank.
|
 |
Aerial February 2003 |
2/12/2003 10:22:44 AM Cofferdam from downstream
|
 |
Aerial February 2003 |
2/12/2003 10:19:34 AM Cofferdam from north bank.
|
 |
Aerial February 2003 |
2/12/2003 10:18:14 AM Cofferdam from upstream.
|
 |
Aerial February 2003 |
2/12/2003 10:16:28 AM Cofferdam from upstream.
|
 |
Aerial February 2003 |
2/12/2003 10:13:46 AM Cofferdam from south bank.
|
 |
Nav Pass |
2/11/2003 2:20:56 PM Completed baffle blocks
|
 |
Nav Pass |
2/10/2003 1:56:36 PM Crest gate bearing placement on Nav Pass
|
 |
Control Tower |
2/7/2003 1:53:08 PM To 196 looking downstream
|